Metal Panel Curtainwall

Installation & Design Considerations

  • Locate insulation horizontally between wall ties directly on back-up wall.
  • Provide 1” minimum clear space between inside brick face and the exterior surface of the insulation board.
  • Abut foam insulation board joints tightly. Cut insulation to fit tightly around vents, louvers, pipes, conduits and other through-wall/insulation penetrations.
  • Joints and openings should be sealed with Owens Corning BILD-R-TAPE®.
  • Provide adequate flashings, functioning weepholes and caulk movement joints.
  • The need for and placement of vapor retarders should be determined by the building designer.
  • Architect must supply detailed drawings to meet project and building code requirements.